Springdale Bond Program

[Download Maps] [Project List]

 
   
Northwest Quadrant Northeast Quadrant
Southwest Quadrant Southeast Quadrant
The map is divided into quadrants and saved as PDF files. Click on a quadrant to open in your browser -or- right click and choose 'save target as..' to download.




 

 


 

CITY OF SPRINGDALE

2003 STREET IMPROVEMENT BOND PROGRAM       

PROJECT STATUS REPORT     [.pdf]

 

 

Southern Corridor

 

BP-0101, Southern Corridor – Carley Road to Turner Street

  • Status:  Under Construction
  • Construction Start:  January 2, 2006
  • Estimated Completion:  March 31, 2009
  • Cost:  $13,279,451.76

 

BP-0102, Southern Corridor – Turner Street to Hwy 265

  • Status:  Right-of-way Acquisition Phase
  • Estimated Bid Date:  May 9, 2007
  • Estimated Construction Time:  635 days
  • Estimated Cost:  $5.1 M

 

BP-0103, Southern Corridor – 40th to 48th Street

  • Status:  Complete

 

BP-0500, Butterfield Coach/Southern Corridor – Hwy 265 to Electric Avenue

  • Status:  Under Construction
  • Construction Start:  October 2, 2006
  • Estimated Completion:  October 10, 2008
  • Cost:  $10,565,680.40

 

 

Central Corridor

 

BP-0201, Central Corridor (Huntsville Ave, Phase I) – Hwy 71B to Old Missouri Road

  • Status:  Under Construction
  • Construction Start:  November 20, 2006
  • Estimated Completion:  November 17, 2008
  • Cost:  $10,991,004.25

 

BP-0202, Central Corridor (Huntsville Ave, Phase II) – Old Missouri Road to Emma Ave

  • Status:  Complete

 

Central Corridor (cont’d)

 

BP-0203, Central Corridor (Huntsville Ave, Phase III) – Emma Avenue to Hwy 412

  • Status:  Right-of-way Appraisal Phase
  • Estimated Bid Date:  July 25, 2007
  • Estimated Construction Time:  575 days
  • Estimated Cost:  $7.2 M

 

 

Northern Corridor

 

BP-0301, Northern Corridor (Wagon Wheel, Phase I) – Hwy 71B to Robins Road

  • Status:  Right-of-way Appraisal Phase
  • Estimated Bid Date:  June 27, 2007
  • Estimated Construction Time:  450 days
  • Estimated Cost:  $6.1 M

 

BP-0302, Northern Corridor (Wagon Wheel, Phase II) – Robins Road to I-540

  • Status:  Preliminary Design Phase
  • Estimated Bid Date:  November 14, 2007
  • Estimated Construction Time:  450 days
  • Estimated Cost:  $8.5M

 

 

Non-Corridor Projects

 

BP-0401, Har Ber Avenue – Jones Road to Hwy 112

  • Status:  Construction is complete

 

 

BP-0402, Har Ber Avenue – 48th Street to Brush Creek

  • Status:  Bid/Award Phase
  • Bid Date:  March 28, 2007
  • Construction Time:  540 days
  • Cost:  $6,056,927.53

 

 

BP-0600, 48th Street – Brush Creek to I-540 exit ramp

  • Status:  Right-of-way Acquisition Phase
  • Estimated Bid Date:  June 13, 2007
  • Estimated Construction Time:  450 days
  • Estimated Cost:  $2.7 M

 

 

BP-0700, Turner Street – Robin Hood Court to Lakeview Drive

  • Status:  Under Construction
  • Construction Start:  January 2, 2007
  • Estimated Completion:  April 5, 2008
  • Cost:  $3,640,316.60

 

BP-0800, Silent Grove Road – Pump Station Road to Del’s Wood Subdivision

  • Status:  Construction is complete

 

 

BP-0900, West End Street – Watson Avenue to Counts Avenue

  • Status:  Final Design Phase
  • Estimated Bid Date:  May 30, 2007
  • Estimated Construction Time:  300 days
  • Estimated Cost:  $2.1 M

 

 

BP-1000, Intersection Improvements – Hwy 412 at Jones Road

  • Status:  Construction is complete

 

 

BP-1001, Intersection Improvements – Hwy 412 at 56th Street

  • Status:  Construction is complete

 

 

BP-1101, Street Overlays – Phase 1

  • Status:  Construction is complete

 

 

BP-1102, Street Overlays – Phase 2

  • Status:  Construction is complete