City of Springdale
 
 
Bond Program

City of Springdale 2003
Street Improvement Bond Program

Contruction Dynamics Group - An Arcadis Company
Project Status Report  [.pdf]pdf icon 
April 29, 2008 

Southern Corridor

 Bp-0101, Southern Corridor - Carley Road to Turner Street

  • Status:  Under Construction By Crossland Construction Co., Inc.
  • Construction Start Date:  January 2, 2007
  • Contract Completion Date:  March 22, 2009
  • Construction Contract Amount:  $12,756,711.76

Bp-0102, Southern Corridor - Turner Street to Hwy 265

  • Status:  Under Construction By Sweetser Construction, Inc.
  • Construction Start Date:  June 18, 2007
  • Contract Completion Date:  March 10, 2009
  • Construction Contract Amount:  $3,624,473.45

Bp-0103, Southern Corridor - 40th to 48th Street

  • Status:  Construction Completed November 19, 2007, By N.E.C. Inc.
  • Construction Cost:   $2,080,388.43

Bp-0500, Butterfield Coach/Southern Corridor - Hwy 265 to Electric Avenue

  • Status:  Under Construction By Apac-Arkansas, Inc., Mcclinton-Anchor Division
  • Construction Start Date:  October 2, 2006
  • Contract Completion Date:  September 30, 2008
  • Construction Contract Amount:  $10,565,680.40

Central Corridor

Bp-0201, Central Corridor (Huntsville Ave, Phase I) - Hwy 71b to Old Missouri Road

  • Status:  Under Construction By Forsgren, Inc.
  • Construction Start Date:  November 20, 2006
  • Contract Completion Date:  November 18, 2008
  • Construction Contract Amount:  $10,991,004.25

Bp-0202, Central Corridor (Huntsville Ave, Phase Ii) - Old Missouri Road to Emma Ave

  • Status:  Construction Completed September 6, 2007, By Dean Crowder Construction, Inc.
  • Construction Cost:  $5,163,655.30

Bp-0203, Central Corridor (Huntsville Ave, Phase Iii) - Emma Avenue to Hwy 412

  • Status:  Under Construction By Dean Crowder Construction, Inc.
  • Construction Start Date:  November 12, 2007
  • Contract Completion Date:  May 5, 2009
  • Construction Contract Amount:  $5,047,027.19

Northern Corridor

Bp-0301, Northern Corridor (Wagon Wheel, Phase I) - Hwy 71b to Robins Road

  • Status:  Under Construction By Sweetser Construction, Inc.
  • Construction Start Date:  October 8, 2007
  • Contract Completion Date:  December 31, 2008
  • Construction Contract Amount::  $4,713,025.00

Bp-0302, Northern Corridor (Wagon Wheel, Phase Ii) - Robins Road to I-540

  • Status:  Under Construction By Apac-Arkansas, Inc., Mcclinton-Anchor Division
  • Construction Start Date:  March 17, 2008
  • Contract Completion Date:  December 7, 2009
  • Construction Contract Amount:  $9,095,639.80

Non-Corridor Projects

Bp-0401, Har Ber Avenue - Jones Road to Hwy 112

  • Status:  Construction Completed December 14, 2005, By Apac-Arkansas, Inc., Mcclinton-Anchor Division
  • Construction Cost:  $2,640,722.27

Bp-0402, Har Ber Avenue - 48th Street to Brush Creek

  • Status:  Under Construction By Wilson Brothers Construction Co., Inc.
  • Construction Start Date:  May 14, 2007
  • Contract Completion Date:  November 4, 2008
  • Construction Contract Amount:  $6,056,927.53

Bp-0600, 48th Street - Brush Creek to I-540 Exit Ramp

  • Status:  Under Construction By Ames Construction Solutions, Llc
  • Construction Start Date:  July 9, 2007
  • Contract Completion Date:  May 4, 2008
  • Construction Contract Amount:    $1,572,947.00

Bp-0700, Turner Street - Robin Hood Court to Lakeview Drive

  • Status:  Under Construction By N.E.C., Inc.
  • Construction Start Date:  January 2, 2007
  • Contract Completion Date:  June 12, 2008
  • Construction Contract Amount:  $3,646,379.30

Bp-0800, Silent Grove Road - Pump Station Road to Del's Wood Subdivision

  • Status:  Construction Completed February 16, 2006, By Mobley Contractors, Inc.
  • Construction Cost:  $1,332,330.12 

Bp-0900, West End Street - Watson Avenue to Counts Avenue

  • Status:  Under Construction By Forsgren, Inc.
  • Construction Start Date:  July 9, 2007
  • Contract Completion Date:  May 4, 2008
  • Construction Contract Amount:  $2,185,767.94

Bp-1000, Intersection Improvements - Hwy 412 At Jones Road

  • Status:  Construction Completed September 29, 2005, By Apac-Arkansas, Inc., Mcclinton-Anchor Division
  • Construction Cost:  $324,310.54

Bp-1001, Intersection Improvements - Hwy 412 At 56th Street

  • Status:  Construction Complete In Capital Improvement Program

Bp-1101, Street Overlays - Phase 1

  • Status:  Construction Completed February 9, 2005, By Apac-Arkansas, Inc., Mcclinton-Anchor Division
  • Construction Cost:  $1,581,399.12

Bp-1102, Street Overlays - Phase 2

  • Status:  Construction Completed September 29, 2005, By Apac-Arkansas, Inc., Mcclinton-Anchor Division
  • Construction Cost:  $1,645,105.53
 

News
Planning Commission Agenda
October 7, 2008
5:00pm City Council
Chambers... More
Highlights
2008 Revised Master Street Plan
Adopted July 22, 2008
 
Copyright © 2007, City of Springdale
Site Powered by Revize