City of Springdale 2003 Street Improvement Bond Program
Contruction Dynamics Group - An Arcadis Company Project Status Report [.pdf] April 29, 2008
Southern Corridor
Bp-0101, Southern Corridor - Carley Road to Turner Street
- Status: Under Construction By Crossland Construction Co., Inc.
- Construction Start Date: January 2, 2007
- Contract Completion Date: March 22, 2009
- Construction Contract Amount: $12,756,711.76
Bp-0102, Southern Corridor - Turner Street to Hwy 265
- Status: Under Construction By Sweetser Construction, Inc.
- Construction Start Date: June 18, 2007
- Contract Completion Date: March 10, 2009
- Construction Contract Amount: $3,624,473.45
Bp-0103, Southern Corridor - 40th to 48th Street
- Status: Construction Completed November 19, 2007, By N.E.C. Inc.
- Construction Cost: $2,080,388.43
Bp-0500, Butterfield Coach/Southern Corridor - Hwy 265 to Electric Avenue
- Status: Under Construction By Apac-Arkansas, Inc., Mcclinton-Anchor Division
- Construction Start Date: October 2, 2006
- Contract Completion Date: September 30, 2008
- Construction Contract Amount: $10,565,680.40
Central Corridor
Bp-0201, Central Corridor (Huntsville Ave, Phase I) - Hwy 71b to Old Missouri Road
- Status: Under Construction By Forsgren, Inc.
- Construction Start Date: November 20, 2006
- Contract Completion Date: November 18, 2008
- Construction Contract Amount: $10,991,004.25
Bp-0202, Central Corridor (Huntsville Ave, Phase Ii) - Old Missouri Road to Emma Ave
- Status: Construction Completed September 6, 2007, By Dean Crowder Construction, Inc.
- Construction Cost: $5,163,655.30
Bp-0203, Central Corridor (Huntsville Ave, Phase Iii) - Emma Avenue to Hwy 412
- Status: Under Construction By Dean Crowder Construction, Inc.
- Construction Start Date: November 12, 2007
- Contract Completion Date: May 5, 2009
- Construction Contract Amount: $5,047,027.19
Northern Corridor
Bp-0301, Northern Corridor (Wagon Wheel, Phase I) - Hwy 71b to Robins Road
- Status: Under Construction By Sweetser Construction, Inc.
- Construction Start Date: October 8, 2007
- Contract Completion Date: December 31, 2008
- Construction Contract Amount:: $4,713,025.00
Bp-0302, Northern Corridor (Wagon Wheel, Phase Ii) - Robins Road to I-540
- Status: Under Construction By Apac-Arkansas, Inc., Mcclinton-Anchor Division
- Construction Start Date: March 17, 2008
- Contract Completion Date: December 7, 2009
- Construction Contract Amount: $9,095,639.80
Non-Corridor Projects
Bp-0401, Har Ber Avenue - Jones Road to Hwy 112
- Status: Construction Completed December 14, 2005, By Apac-Arkansas, Inc., Mcclinton-Anchor Division
- Construction Cost: $2,640,722.27
Bp-0402, Har Ber Avenue - 48th Street to Brush Creek
- Status: Under Construction By Wilson Brothers Construction Co., Inc.
- Construction Start Date: May 14, 2007
- Contract Completion Date: November 4, 2008
- Construction Contract Amount: $6,056,927.53
Bp-0600, 48th Street - Brush Creek to I-540 Exit Ramp
- Status: Under Construction By Ames Construction Solutions, Llc
- Construction Start Date: July 9, 2007
- Contract Completion Date: May 4, 2008
- Construction Contract Amount: $1,572,947.00
Bp-0700, Turner Street - Robin Hood Court to Lakeview Drive
- Status: Under Construction By N.E.C., Inc.
- Construction Start Date: January 2, 2007
- Contract Completion Date: June 12, 2008
- Construction Contract Amount: $3,646,379.30
Bp-0800, Silent Grove Road - Pump Station Road to Del's Wood Subdivision
- Status: Construction Completed February 16, 2006, By Mobley Contractors, Inc.
- Construction Cost: $1,332,330.12
Bp-0900, West End Street - Watson Avenue to Counts Avenue
- Status: Under Construction By Forsgren, Inc.
- Construction Start Date: July 9, 2007
- Contract Completion Date: May 4, 2008
- Construction Contract Amount: $2,185,767.94
Bp-1000, Intersection Improvements - Hwy 412 At Jones Road
- Status: Construction Completed September 29, 2005, By Apac-Arkansas, Inc., Mcclinton-Anchor Division
- Construction Cost: $324,310.54
Bp-1001, Intersection Improvements - Hwy 412 At 56th Street
- Status: Construction Complete In Capital Improvement Program
Bp-1101, Street Overlays - Phase 1
- Status: Construction Completed February 9, 2005, By Apac-Arkansas, Inc., Mcclinton-Anchor Division
- Construction Cost: $1,581,399.12
Bp-1102, Street Overlays - Phase 2
- Status: Construction Completed September 29, 2005, By Apac-Arkansas, Inc., Mcclinton-Anchor Division
- Construction Cost: $1,645,105.53
|