Sec. 18-97. Procedure for construction plan approval.

Licensees for commercial aeronautical activity at the municipal airport shall follow the following procedure for approval of construction plans:

(1) Preparation of plans. All plans and specifications for buildings or structures to occupy space obtained through the airport commission shall be prepared by a licensed architect and submitted with the architect's seal to the airport commission for review.

(2) Submission. The licensee shall submit to the airport commission an application for preliminary approval of plans and specifications for any proposed building or structure to occupy space obtained through the commission and three copies of the plans and specifications of any proposed building or structure to the city clerk at least 15 days prior to a meeting of the airport commission at which consideration is requested. The airport commission will in writing advise the licensee as promptly as possible of the extent to which the proposed building or structure conforms to the requirements of the Springdale Municipal Airport master plan, the city planning commission, and other city, county, state and federal agencies that may be associated with the development of the airport, and will discuss possible modification if necessary to secure conformance; provided, further, that all prospective airport tenants and licensees shall submit to the Federal Aviation Administration prior to commencement of any construction a "Notice of Proposed Construction or Alteration" on FAA Form 7460-1 as required by Part 77 of the Federal Aviation Regulations.

(3) Airport commission action. Within 90 days after acceptance for review of the preliminary plans and specifications by the airport commission, it shall indicate in writing its approval, disapproval or approval with condition. Failure of the airport commission to act on the preliminary plans and specifications within 90 days of its acceptance will be deemed approval of the plans and specifications. Approval, approval with conditions or disapproval of the preliminary plans and specifications by the airport commission shall be noted, both upon the preliminary plans and the airport commission records.

(Code 1973, § 3-48)